WEEKS 15 to 17 - 11/13/11 - 12/03/11

Framing progressed as blocking of interior walls and trusses was performed inside, along with the framing of the stage for the cultural hall. Meanwhile, sheathing of the roof and walls continued on exterior of the building. HVAC ducts were installed in the walls near the chapel area and in the attic spaces above the building entrances. The process of roughing in the plumbing lines and installing wall outlets continued as the plumbers and electricians worked throughout the building.