The irrigation and landscape are 95% complete. We have completed the paint, acoustical ceiling tile, ceramic tile, and sisal wall coverings. The millwork, doors, and cabinets are being installed. The wood floor has started and will be finished in approximately 2 weeks. The mechanical, electrical, and plumbing contractors are working on trim and finishes. Carpet has tentatively been scheduled for June 4.