Tuesday, October 25, 2011

WEEKS 9 to 11 - 10/02/11 - 10/22/11

Work has been performed on the parking area as lime stabilization materials were spread and compacted into the soil to create a stronger base for concrete parking lot. Forms were erected while rebar was placed and tied in preparation for the concrete that would later be poured and finished by hand. The lumber package arrived on site and the beginning stages of framing began as work was performed on the exterior walls.

Lime Stabilization



Rebar Concrete Pour Framing Lumber Package 7-Day Weather Forecast

Monday, October 3, 2011

WEEKS 7 & 8 - 09/18/11 - 10/01/11

The installation of the vapor barrier for the building has been completed and all of the rebar has been tied in preparation for the pouring of the concrete slab. Lightning protection cables have been installed and tied into the foundation rebar. Concrete trucks arrived and poured while the crews worked to spread the concrete, install hold-down anchors and finish the surface of the building pad.

Vapor Barrier and Rebar





Rebar and Lightning Protection Cable



Concrete Pour



Concrete Finishing