Monday, December 5, 2011

WEEKS 15 to 17 - 11/13/11 - 12/03/11

Framing progressed as blocking of interior walls and trusses was performed inside, along with the framing of the stage for the cultural hall. Meanwhile, sheathing of the roof and walls continued on exterior of the building. HVAC ducts were installed in the walls near the chapel area and in the attic spaces above the building entrances. The process of roughing in the plumbing lines and installing wall outlets continued as the plumbers and electricians worked throughout the building.

Framing and HVAC Ducts


























Blocking


7-Day Weather Forecast


Thursday, November 17, 2011

WEEKS 12 to 14 - 10/23/11 - 11/22/11

Concrete forms were placed and rebar was tied in preparation for the concrete pour. Large sections of the parking area were completed as concrete was poured and finished. Once the concrete had sufficiently cured, control joints were cut into the concrete pavement. While work was being performed on the parking areas, framing crews continued to frame and sheath the exterior walls of the building. Roof trusses and rafters have now been erected and placed over the majority of the roof areas.

Concrete Forms and Rebar
Concrete Pour and Finish










Saw Cuts





Exterior Wall Framing





Exterior Sheathing and Trusses


























7-Day Weather Forecast


Tuesday, October 25, 2011

WEEKS 9 to 11 - 10/02/11 - 10/22/11

Work has been performed on the parking area as lime stabilization materials were spread and compacted into the soil to create a stronger base for concrete parking lot. Forms were erected while rebar was placed and tied in preparation for the concrete that would later be poured and finished by hand. The lumber package arrived on site and the beginning stages of framing began as work was performed on the exterior walls.

Lime Stabilization



Rebar Concrete Pour Framing Lumber Package 7-Day Weather Forecast

Monday, October 3, 2011

WEEKS 7 & 8 - 09/18/11 - 10/01/11

The installation of the vapor barrier for the building has been completed and all of the rebar has been tied in preparation for the pouring of the concrete slab. Lightning protection cables have been installed and tied into the foundation rebar. Concrete trucks arrived and poured while the crews worked to spread the concrete, install hold-down anchors and finish the surface of the building pad.

Vapor Barrier and Rebar





Rebar and Lightning Protection Cable



Concrete Pour



Concrete Finishing