Thursday, November 17, 2011

WEEKS 12 to 14 - 10/23/11 - 11/22/11

Concrete forms were placed and rebar was tied in preparation for the concrete pour. Large sections of the parking area were completed as concrete was poured and finished. Once the concrete had sufficiently cured, control joints were cut into the concrete pavement. While work was being performed on the parking areas, framing crews continued to frame and sheath the exterior walls of the building. Roof trusses and rafters have now been erected and placed over the majority of the roof areas.

Concrete Forms and Rebar
Concrete Pour and Finish










Saw Cuts





Exterior Wall Framing





Exterior Sheathing and Trusses