Monday, January 23, 2012

WEEKS 23 & 24 - 01/08/12 - 01/21/12

The exterior walls of the building have been wrapped with Tyvek Home Wrap in preparation for the masonry work to proceed. We look forward to the arrival of the steeple which is scheduled for Thursday, January 26th. Temporary lighting has been extended throughout the interior and batt insulation has been installed in the cavities of the interior walls and ceilings. Gypsum board has arrived on site and will soon be applied to the walls and ceiling surfaces.

Tyvek Home Wrap









Batt Insulation



Gypsum Board