Monday, February 13, 2012

WEEKS 25 to 28 - 01/22/12 - 02/18/12

The highly anticipated arrival of the steeple took place during the past few weeks. It was raised and installed with the use of a crane while the process of installing storefront doors and windows began at the main entrances and chapel areas. The interior of the building received the installation of gypsum board on the ceilings and corridor walls. Drywall tape and joint compound has been applied to many of the walls and ceiling surfaces and continues to progress throughout the building. HVAC ducts were installed in the mezzanine ceiling areas while electricians continued to rough-in interior walls.

Steeple
















Storefront Doors


















Gypsum Board






























HVAC Ducts