The masonry work around the exterior of the building has been completed with the exception of the screen walls for the mechanical pads. The footings for these walls have been formed and poured and masonry work will begin once the weather permits for exterior work. We have had some delays due to the continual rains that have come through the Houston area. But work continues to progress inside as the taping and bedding of drywall continues, the framing of the rostrum nears completion and the HVAC crews continue to work in the mezzanine areas.
Masonry
No comments:
Post a Comment